Daytime

• Buckingham Road: Tuesday from 7 a.m. to 5 p.m.

• 350 Pleasant Valley Way in front of the Wilshire Grand Hotel: Tuesday and Thursday from 8:30 a.m. to 4 p.m. 

• Northfield Avenue at Walker Road: Tuesday from 7 a.m. to 4 p.m.

• Mt. Pleasant Avenue at Longview Street: Thursday from 9 a.m. to 3 p.m.

Evening

• Northfield Avenue at Walker Road: Wednesday, Friday and Saturday from 1 a.m. to 6 a.m.; Thursday from 7 p.m. to 1 a.m.  

County Road Work

•  Essex County crews will continue work on . Crews will work on different portions of the roadway starting in West Orange and move their way up toward Livingston.

Expect to see crews on the road Monday through Friday from 8 p.m. to 5 a.m. 

To date, the Northfield Avenue has been repaved up to about Prospect Avenue. 

Unfortunately, the West Orange Patch does not have an eye in the sky with its own traffic helicopter like other news organizations. So for these posts to be the most successful, the West Orange Patch counts on residents driving around town to post updates about what they see and where traffic is. Post what you see in the comment section below.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something